Decision details

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Decisions:

 

The Service Director, Frontline Services presented to Cabinet the report, which proposed the addition of carriageway and footway maintenance schemes to the pool of previously approved schemes, further to the approval of the Highways, Transportation and Strategic Projects Capital Programme approved on 6th May 2020 and subsequent to the report to Cabinet of 24th September 2020.

 

The Service Director drew Members’ attention to Appendix 1, which included a further £2.210M of carriageways schemes and a further £0.496M of footways schemes to be added to the already approved pool. 

 

The Leader was happy to support the recommendations and spoke of positive progress made in terms of delivery of schemes, despite the Covid-19 restrictions such as lockdowns and interruptions to supply and staffing. The Leader then referred to the efficient delivery of schemes, during Welsh Government’s two week ‘Firebreak’ Lockdown, when traffic was lighter.

 

The Cabinet RESOLVED:

1.    To note and approve the addition of the schemes listed in Appendix A of the report to the pools of previously approved schemes.

 

Publication date: 17/11/2020

Date of decision: 17/11/2020

Decided at meeting: 17/11/2020 - Cabinet

Effective from: 24/11/2020

Accompanying Documents: